If 6 Men Can Do A Piece Of Work In 14 Days, How Many Men Are Needed To Do The Work In 21 Days?

If 6 Men Can Do A Piece Of Work In 14 Days, How Many Men Are Needed To Do The Work In 21 Days?. Need a bit more clarification? Continuing it would take one man84 days (3 x 28) to.

News of the Week News of the Week Announcements
News of the Week News of the Week Announcements from myllu.llu.edu

6 men in 14 days. 84 men days = x men * 21 days. If it is done within 21 days, need x men.

Web Up To 15% Cash Back If 6 Men Can Do A Piece Of Work In 14 Days, How Many Men Are Needed To Do The Work In 21 Days?


To do the job in 21 days would take 4 men (84 / 21) answer by ray100 (1637) ( show source ): You can put this solution on your. X men in 21 days.

84 Men Days = X Men * 21 Days.


It takes one person 84 days to do a piece of work (6 times 14), so it would take 4 men to do it in 21 days. The answer should be 9 workers due to 7 day periods. Web advanced user of windows.

We Have A Direct Variation Here.


6 men * 14 days. You would need 9 poeple. Need a bit more clarification?

Let 'X' Represent The Number Of Men Needed To Do The Work Is 21 Days.


The rate is 6/14=3/7 men/day. Click here to see the equation solved for x. Web if 6 men can do a piece of work in 14 days, how many men are needed to do the work in 21 days?

21 Days So 3/7*21= 9 Men Needed.


Web 6 men in 14 days. Web latest book aptitude question solution: Let x be the number needed to do the job in 21 days.